PROJECT SUMMARY:
Bond funded work at Spring Mountain Elementary was completed in 2008.  Work included improvements to the play equipment area, new stair treads, improved sound system in the gym, upgraded security system and acoustical improvements in the media center.



PROJECT TEAM:
Capital Project Manager:  Garry Kryszak, North Clackamas School District
 Project Manager:  Jon Sandstrom, J.J. Henri Co., Inc.
Dan Golden, District Project Manager
 Architect: Barrentine, Bates & Lee
 Contractor:  TBD
 Engineer: N/A

 
PROJECT SCHEDULE:
 Construction Start:  June ,2008
 Completion Date:  September, 2008
 

UPCOMING ACTIVITIES:
  • All Bond work at Spring Mountain Elementary was completed in September 2008.

PROJECT PHOTOS:

   

Playground w/New Chips and Rubberized Matt

 Sound Barrier in Media Center
 Framing Detail
New Stair Tread